Completed Projects

Sr. No.Project Description  StatusContract Value (INR)
    1Construction of Branch Buildings in BHEL Complex (MP Nagar), Bhopal, Madhya PradeshCompleted ₹          12,74,23,000.00
    2Construction of Sukhdham Co-operative Group Housing Society – 105 Dwelling Units in a 4-Storey Housing Complex including Civil, MEP, and Internal Road Works, Rohini, DelhiCompleted ₹          24,90,00,000.00
3Construction of 100 Dwelling Units in Four Multi-Storey Blocks including Civil, MEP, and Internal Road Works at Dalu Pura, DelhiCompleted ₹          25,80,12,000.00
4Construction of Two Branch Buildings in BHEL Complex (Barkheda & Govindpura), Bhopal, Madhya PradeshCompleted ₹          16,98,54,000.00
5Construction of a 4-Storey Residential Housing Complex including Civil and MEP Works at Rohini, DelhiCompleted ₹          12,50,00,000.00
6Construction of a Housing Complex in BHEL Complex, MP Nagar, Bhopal, Madhya PradeshCompleted ₹          18,35,00,000.00
7Construction of Navodaya School at NarnaulCompleted ₹          21,70,92,000.00
8Construction of a Factory Building at FaridabadCompleted ₹          15,20,05,000.00
9Construction of a School Building at Jaipur, RajasthanCompleted ₹            4,78,28,925.00

       
Sr.  Project Description    Status  Contract Value (SR Million)
1 Construction of Bridges for Saudi Bahrain Causeway at Dhahran, Saudi Arabia Completed 18.62
2 Civil Works for MODA Hangars Project in Dhahran Completed 13.5
3 Construction of 25 Residential Villas at at Jubail Saudi Arabia Completed 14.85
4 Construction of 4 Residential Villas at Riyadh, Saudi Arabia Completed   2.85
5 Construction of 2 School buildings at Ar Ar, Saudi Arabia Completed 21.8
6 Construction of Factory Building, Riyadh, Saudi Arabia Completed    9.5
7 Construction of Private Villas, Riyadh, Saudi Arabia Completed 13.75
8 Construction of Multistoried Building at Dhahran Completed    6.3

Sr.  Project     Description   Status Contract Value (DHS Million)
1 23 Low Cost Houses at Madeena Zayed Al-Dhaffrah, Abu DhabiCompleted19.55
2 10 Low Cost Houses at Shawamekh, Abu DhabiCompleted  9.85
3 Construction of labour accommodation at Jabel Ali Industrial Area, DubaiCompleted  1.5
4 Construction of Workshop Plant at Jebel Ali Industrial Area, DubaiCompleted  0.5
5 Construction of Multistoried Building for Khalifa Committee at Abu DhabiCompleted  3.74
6 Construction 18 Low Cost Houses at Ghayati Abu DhabiCompleted17.85
7 Construction of Multistoried Building for Khalifa Committee at Abu DhabiCompleted  5.5

Sr.  Project Description    Status  Contract Value (DHS Million)
1   Construction of Foundation for 20 KM 66 KV Overhead Transmission Lines at Sauk  al Khamish Tripoli  Completed     2,00,000.00
2   Construction of 100 Km 66KV Overhead Transmission Lines at Grayan to Zen tan Tripoli  Completed   18,50,000.00
3   Construction of Concrete works for 300,000m3 reservoir at GHARAYAN, Libya  Completed   46,00,161.00
4   Construction of 3 Nos.220 KV Sub-Stations at Tripoli  Completed    67,50,000.00
5   Construction of 4 Nos.400 KV Sub-Stations at Tripoli, Sebha, Misurata and Benghazi  Completed  1,61,61,020.00
6   Construction for 52 KM Road project including bridges and box culverts from Sebha to Houn  Completed  1,31,21,115.00
7   Construction for 37 KM Road project including bridges and box culverts from Al Khoms to Misurta  Completed     95,79,346.00

Sr.     Project
   Description 
  Status  Contract Value (DHS Million)
1    Development of  Muscat International Airport –MC3  Completed   45,03,691.00
2    Construction of RCC Box Culverts at Bid Bid – Sur Dual Carriageway.  Completed  8,97,000.00
3    Construction of Bridge Houses at Muscat International Airport MC1.  Completed  4,84,000.00
4    Construction of RCC Box Culverts at Muscat International Airport MC1.  Completed  5,50,000.00
5    Construction of RCC Box Culverts at Bid Bid – Sur Dual Carriageway.  Completed  3,50,000.00
6    Construction of foundation and floor finishing work  Completed     45,000.00
7    Construction of 4 Villas Residential Complex at Madinat Sultan Qaboos, Muscat  Completed  4,50,000.00
8    Construction of Concrete foundations and slabs for Industrial Sheds for Okrat Petrochemical at Salalah  Completed  1,46,875.00
9    Construction of G+5 Commercial/Residential Building at North Ghubrah, Muscat  Completed  6,81,250.00
10    Construction of G+4 Commercial/Residential Building at Al Hail, Muscat  Completed  4,65,625.00
11    Extension of 3 Floors + penthouse at Al Khuwair, Muscat  Completed  2,60,625.00
12    Construction of Residential/Commercial Complex at Sohar  Completed     85,000.00
13    Construction of Private Residential Villa at Qurm, Muscat Completed  1,80,000.00
14    Modification to Main Entrance and Construction of Lift Shaft at Residential Villa at Madinat Qaboos, Muscat  Completed  1,60,000.00